Toilet & Bathroom Waterproofing Singapore

Toilet and bathroom waterproofing, done under the tiles and proved by a flood test.

The tiles are not the waterproofing. The membrane beneath them is, and it is only ever as good as the trap, the pipes and the wall turn-ups. Rayson makes the membrane and publishes its data; an applicator in our network hacks, applies, flood-tests and re-tiles.

HDB & condo toiletsFlood test at 24 h2026 cost rangesHDB rules

Reviewed: September 2026

The short answer

Hack, membrane, flood test, tile. In that order, every time.

A Singapore toilet or bathroom is waterproofed beneath the tiles. After hacking, a liquid membrane is rolled across the whole floor, into the floor trap, around every pipe and up the walls, flood-tested for 24 hours and only then tiled. Rayson SealForce WB20 is the one-part, water-based membrane for that layer, applied in two coats at 0.4 mm wet film. Singapore price guides checked in September 2026 put a full hack, re-membrane and re-tile of one HDB or condominium toilet at about S$3,000 to S$8,000. Rayson specifies and supplies the membrane; an applicator in the Rayson network assesses, quotes, installs, flood-tests and re-tiles under its own workmanship warranty.

Start with your situation

Four bathrooms, four different first steps.

Each one ends at the same membrane. What changes is what has to happen before it goes on, and who has to agree.

01 / RENOVATING

An HDB or condo toilet being hacked and re-tiled

The clean case. Hacking under the HDB permit, the membrane the day after, the flood test the day after that, then the tile bed. Budget the S$3,000 to S$8,000 range for the whole job.

See the sequence
02 / LEAKING

A stain or drip on the ceiling below

The failed detail is in the toilet above, so the repair happens up there. In an HDB flat the cost is shared under HDB’s scheme; in a condo the strata law presumes the unit above.

Who pays, and what the repair is
03 / NEW FLAT

A BTO under three years old

HDB restricts hacking the wet-area tiles for the first three years to protect the original waterproofing and its warranty. Overlay is the compliant route; the membrane beneath stays untouched.

How long the membrane lasts
04 / LANDED

Bathrooms, balconies and the car porch

The bathrooms inside fail at the same five details. Balconies and the porch are wet areas open to the sky, and take the same membrane under screed and tiles.

The landed-home guide
The job, step by step

What a wet area looks like between the membrane and the tiles.

Photographs from the pre-launch trial application of SealForce WB20 in an HDB toilet in Hougang, September 2026, taken after the membrane coats and during the flood test.

  1. 01

    Hack and prepare

    Tiles, bed and loose material out under the HDB permit, on weekdays between 9 am and 5 pm. The screed is checked for falls to the trap, cracks are reinstated, protrusions removed and the floor left clean and dry.

  2. First coat of green membrane across the whole hacked toilet floor and up the walls
    02

    The whole floor, and every wall

    The first coat is rolled edge to edge and carried up every wall above the finished floor level, so the tiles later sit on one continuous film.

  3. Membrane dressed up and around the base collar of the soil stack in the corner
    03

    Dressed around the stack

    The film turns up the base of the soil stack and along the corner behind it. A pipe through the slab is the first place a bathroom leaks when the film stops short of it.

  4. Membrane worked around the raised WC outlet collar with the wall turn-up behind
    04

    Into the outlet, up the wall

    At the WC outlet the film is worked to the collar rather than feathered short of it. The turn-up behind shows the brush build the wall junction needs.

  5. Cured membrane around two open pipe cores, checked for pinholes
    05

    Second coat, pinholes closed

    The second coat goes on 1 to 2 hours after the first, at 0.4 mm wet film. Any thin patch or pinhole gets a further coat before the test, never after the tiles.

  6. Flood test in progress, the floor filled with water over the membrane with the outlet plugged
    06

    Flood test, then tile

    Twenty-four hours after the final coat the outlet is plugged and the floor flooded for a full day. The ceiling below stays dry, or the membrane is made good before anything covers it.

Reference for the wet-area duty: a controlled, pre-launch application of the membrane this page specifies. SealForce WB20 is part of Rayson's upcoming release.

The numbers

What it costs, how long it takes, what the membrane takes.

Market ranges from Singapore price guides checked on 25 September 2026, not Rayson quotations. The material lines come from the SealForce WB20 data sheet.

WHAT IT COSTS · PER TOILET
Membrane line within a renovation
S$400 – 1,500
Full hack, re-membrane, re-tile
S$3,000 – 8,000+
No-hack repair from above
S$700 – 2,500
Typical HDB ceiling leak, fixed at source
S$600 – 1,800
The full cost tables and their sources
HOW LONG IT TAKES
Hacking, on HDB weekday hours
1 – 3 days
Membrane, two coats
1 day
Flood test after the final coat
24 h, held a day
Then screed, tiles, grout
Within the permit window
The day-by-day guide
WHAT THE MEMBRANE TAKES
SealForce WB20, two coats
0.4 mm wet film each
Consumption per coat
About 0.56 kg/m²
A typical toilet with turn-ups
8 – 12 kg, under one 20 kg pail
Material warranty
3 years against defects
SealForce WB20 TDS (PDF)
Renovation permitHacking and re-tiling in an HDB flat need a permit through a registered renovation contractor; the permit fixes the demolition days.
Noisy work hoursHacking, removing finishes and cutting tiles: weekdays 9 am to 5 pm only, never Saturdays, Sundays or public holidays.
New flatsNo hacking of bathroom wall and floor tiles for three years from key collection; it voids the waterproofing warranty. Overlay instead.
Ceiling leaksThe slab between two flats is shared. HDB’s Goodwill Repair Assistance scheme co-pays half; the owners share the rest. Verify the current terms with HDB.
Published system evidence

One membrane for the tiled wet area. Two more for what sits beside it.

Starting routes, not a specification. Open the data sheet before committing to preparation, film build or timing.

TOILET + BATHROOM / ONE-PART, BENEATH TILES

SealForce WB20

One-part, water-based, polyurethane-modified membrane rolled straight from the pail in two coats at 0.4 mm wet film. No primer, no mixing, low odour in an occupied home. Elongation of at least 150%, bridges a 2 mm crack, flood-tested 24 hours after the final coat and protected by the tile bed.

DECK + HEAVY-DUTY WET AREA / TWO-COMPONENT

SealForce RC30

Two-component, roller-applied polyurea-based membrane with elongation above 500% for decks that carry vehicles, plant-room floors and heavier-duty wet areas.

CRACKS, VOIDS AND FILLETS / REPAIR

PatchBond TX80

Non-sag epoxy repair compound for reinstating cracks and voids and forming the fillet at the wall–floor junction before the membrane goes on.

Hack, or no-hack?

The honest answer depends on one test.

Is the membrane under the tiles sound? No-hack is honest when a flood test holds, the ceiling below stays dry under test, and the symptom is water weeping through grout or a cracked tile; re-grouting, a grout sealer and replacing the cracked tile address the actual fault. Hacking is unavoidable when the flood test fails, the leak tracks to the trap, a pipe or the wall junction, or the membrane was never installed, which in older flats it often was not. A failed HDB or HIP water test means water is already under the tiles, which puts the bathroom in the second case.

A contractor who quotes for hacking without a test, or for a sealer without one, is guessing with your money. The contractor guide sets out what a quotation for this work must show, and the wet-area guide goes through the five details where nearly every Singapore bathroom leaks.

Ready for a useful first review?

Show us the toilet, and the ceiling below it.

Send photographs of the floor, the trap, the shower wall and the threshold, and of any stain or drip underneath; the age of the bathroom; whether it is HDB, condo or landed; and your renovation dates. We respond within one working day, including when the honest answer is a re-grout rather than a hack.

Frequently asked questions

How much does toilet waterproofing cost in Singapore?

Singapore price guides checked in September 2026 put the waterproofing membrane line at S$400 to S$1,500 within a bathroom renovation, and a full hack, re-membrane and re-tile of one HDB or condominium toilet at about S$3,000 to S$8,000 when a waterproofing contractor carries the whole job. Hacking and disposal alone is S$400 to S$1,500 and tiling S$1,500 to S$6,500; a no-hack repair from above is S$700 to S$2,500. The membrane material is the small part: two coats of Rayson SealForce WB20 on a typical toilet with its turn-ups take about 8 to 12 kg, under one 20 kg pail.

How long does toilet waterproofing take?

Hacking one to three weekdays, because HDB permits noisy work only on weekdays from 9 am to 5 pm and fixes the demolition days in the renovation permit; the membrane one day, in two coats a few hours apart; the flood test the following day, 24 hours after the final coat; then the screed, tiles and grout. On the Hougang trial application of SealForce WB20 photographed in September 2026, the membrane was complete the day after the approved hacking window closed and the flood test was under way the next afternoon.

Can my toilet be waterproofed without hacking the tiles?

A membrane cannot be applied over tiles: SealForce WB20 goes onto the prepared screed beneath them. A no-hack treatment is honest only for a narrow set of faults, such as water weeping through grout over a membrane that is still sound. If the bathroom has failed an HDB or HIP water test, water is already under the tiles, and injections or surface sealers buy months, not years. An assessment with a flood test tells you which case you have before anyone quotes for hacking.

What is the flood test, and how long is it held?

After the final coat has dried for 24 hours and before any screed or tile goes down, the floor trap is plugged and the whole floor is flooded to a set depth and left for a full day while the ceiling below and the adjoining rooms are checked. It is the only proof that the membrane works. A quotation that does not include it is missing its most important line.

My BTO flat is under three years old. Can the toilet be hacked?

HDB restricts the hacking of bathroom and toilet wall and floor tiles in new flats for the first three years from key collection, to keep the original waterproofing and its warranty intact; hacking inside that window voids the waterproofing warranty. The compliant route is an overlay that leaves the tiles and the membrane beneath them undisturbed. Confirm the current terms on HDB's renovation guidelines before you plan.

The ceiling below my toilet is stained. Who pays?

In an HDB flat the floor slab between two flats is a shared structure, and HDB's Goodwill Repair Assistance scheme has been described in HDB's own letters as co-paying 50% of the repair cost, with the remaining half shared equally between the upper and lower owners and HDB arranging the contractor once both agree. In a condominium the strata law presumes the leak comes from the unit above unless proven otherwise, and both owners investigate jointly with the management corporation involved where needed. The repair is always done from the toilet above.

How high must the membrane go up the walls?

The practice Singapore specifications follow, drawn from the BCA good industry practices guide for internal wet areas, carries the membrane up every wall well above the finished floor, with about 300 mm as the common minimum, and to around 1,800 mm or full height on the walls that shower water strikes. It also rises behind the door threshold or kerb, and is dressed into the floor trap and up every pipe sleeve.

Which Rayson product is used, and how much does a toilet need?

Rayson SealForce WB20, a one-part, water-based, polyurethane-modified membrane rolled straight from the pail in two coats at 0.4 mm wet film each. A typical 3 m² toilet with 300 mm turn-ups and a shower wall to 1.8 m takes about 8 to 12 kg, under one 20 kg pail. Where the wet area is heavier duty, a deck that carries vehicles or a plant-room floor, the two-component polyurea SealForce RC30 takes over.

What warranty do I get?

Two separate warranties. Rayson warrants SealForce WB20 against manufacturing defects for three years from the date of supply, provided the material is applied per the technical data sheet and the membrane is flood-tested before it is covered; the remedy is replacement material. The applicator warrants its workmanship on its own quotation. Ask for both in writing.

Who does the work, Rayson or a contractor?

An applicator in the Rayson network. Rayson manufactures and supplies the membrane and publishes its technical data; the applicator inspects the bathroom, issues the quotation and invoice, hacks, prepares, applies the membrane, flood-tests and re-tiles under its own workmanship warranty. Send us photographs of the toilet and of any stain below and we will specify the system and introduce an applicator.

Not sure which system fits your project?

Tell us your surface, area and timeline — our Singapore technical team will recommend a practical system and price it fast.